Back to all articlesVariance analysis by the week: a template for annual targets
Claire HolmanClaire Holman
Finance

Variance analysis by the week: a template for annual targets

Variance analysis compares actual results with a plan, budget, or forecast, and explains the difference. Calculate each variance as actual minus plan, in units and as a percent of plan, and label it favorable or unfavorable by its effect on the goal. When an annual target depends on weekly work, run the comparison every week against a seasonally weighted goal, and track two more numbers: the cumulative gap and the weekly rate needed to finish on target.

Teams that check an annual target monthly or quarterly often find the shortfall in the autumn and spend the last weeks of the year rushing to close it. A weekly row per target finds the same gap months earlier, while it is small enough to recover at a normal pace.

The four numbers in each weekly row

The Association for Financial Professionals (AFP) defines variance analysis as "a quantitative method for assessing the difference between planned and actual financial outcomes." Its basic formula is actual result minus budgeted amount. A favorable variance is better than expected and an unfavorable one is worse, and the line decides which direction counts as better. Revenue above budget is favorable. An expense above budget is unfavorable.

A count of completed work follows the revenue convention, because more is better. AFP also recommends recording each variance both as an absolute value and as a percentage, since a large percentage on a small base can be immaterial in absolute terms. The template tracks four measures:

  • Variance: actual minus goal, in jobs.
  • Variance percent: variance divided by goal.
  • Cumulative variance: cumulative actual minus cumulative goal, year to date.
  • Required weekly rate: jobs still needed to reach the annual target, divided by the weeks left.

The same method serves an FP&A team comparing budget with actuals, and any annual target delivered week by week, such as service visits or the inspections a regulator expects each year.

Weighting the annual target by season

The even split divides the annual target by 52, so 5,200 jobs become 100 a week. For seasonal work it misleads. If field work slows in winter, an even split reports a shortfall every winter week and hides one every summer week.

Seasonal weighting gives each quarter or month a share of the annual target, based on history or known constraints, then divides each share by the weeks in the period. The weights must sum to 100%. The team in the example below uses these:

QuarterWeightQuarter targetWeeksWeekly goal
Q118%9361372
Q228%1,45613112
Q332%1,66413128
Q422%1,1441388
Year100%5,20052100 on average

Settle a few definitions before the weights go in: the baseline version of the plan, the day a week ends, and what counts as a completed job. Count each job in the week it was completed, whatever its scheduled date, and decide how reopened work counts. If the plan changes mid-year, keep the original and report against both versions, so a reset goal cannot erase a real shortfall.

The template, one row per week

ColumnHow to calculate it
WeekWeek number in the plan year
Weekly goalQuarter target divided by weeks in the quarter
ActualJobs completed that week
VarianceActual minus weekly goal
Cumulative goalSum of weekly goals to date
Cumulative actualSum of actuals to date
Cumulative varianceCumulative actual minus cumulative goal
Required weekly rateAnnual target minus cumulative actual, divided by weeks left

Readers who think in percent may want a cumulative variance percent column too. On a seasonal plan, set the required weekly rate beside the plan's own average for the weeks left, which is the annual target minus the cumulative goal, divided by the weeks left. Measured against this week's goal, the required rate climbs through a light first quarter even for a team exactly on plan.

Three regions, one late crew, and week 26

An operations manager owns a target of 5,200 completed jobs for the year across three regions. North carries 1,300 of it, Central 1,950, and South 1,950. Each region uses the same quarterly weights, so the weekly goals are 18, 27, and 27 in Q1, then 28, 42, and 42 in Q2. The plan assumed South would add seasonal contract crews at the start of Q2. They started in week 21. The team, its regions, and every count below are invented for this post, and each total was rechecked in Python.

Team totals for Q2, with week 13 as the carry-in:

WeekWeekly goalActualVarianceCumulative goalCumulative actualCumulative varianceRequired weekly rate
1372720936934-2109.4
1411295-171,0481,029-19109.8
1511295-171,1601,124-36110.2
1611296-161,2721,220-52110.6
1711294-181,3841,314-70111.0
1811292-201,4961,406-90111.6
1911295-171,6081,501-107112.1
2011295-171,7201,596-124112.6
21112107-51,8321,703-129112.8
22112109-31,9441,812-132112.9
23112110-22,0561,922-134113.0
24112109-32,1682,031-137113.2
25112109-32,2802,140-140113.3
26112108-42,3922,248-144113.5

By the end of week 26, the team had completed 2,248 jobs against a cumulative goal of 2,392, a cumulative variance of -144 jobs, or -6.0%, unfavorable. Finishing at 5,200 takes 2,952 more jobs in 26 weeks, or 113.5 a week. The plan's own average for the second half is 108 a week (2,808 divided by 26), so the required pace runs 5.1% above plan. Spread across the seasonal shape, that means 134.6 a week in Q3 against a goal of 128, and 92.5 a week in Q4 against 88.

The weekly and cumulative columns tell different stories. From week 21 the weekly variance is only -2 to -5, and a manager who reads the latest week sees a team nearly back on plan. Meanwhile the cumulative variance holds near -144 and the required rate keeps climbing, because nothing has recovered the jobs lost in weeks 14 to 20.

An even split would have told a third story. At week 13 it reports 934 jobs against 1,300, a variance of -366 (-28.2%), for a team that is on plan. At week 26 it reports -352 (-13.5%), more than twice the real gap.

Waiting makes the same gap expensive. If the team runs exactly at plan until week 44 and only then tries to recover the 144 jobs, the last eight weeks need 106 a week against a Q4 goal of 88, 20.5% above plan.

What a monthly check would have missed

AFP notes that teams usually produce variance reports as part of the period-end close. That cadence suits a finance budget. On an operational target, a month-end check lets a shortfall run four or five weeks before anyone sees it, and each week adds to the gap.

The table above shows the difference. A weekly check produced seven readings between the first short week and the week South's crews arrived. If the first Q2 month covers weeks 14 to 17, a monthly review produces one reading in that span, at week 17, by which time the region at fault was 62 jobs behind.

Weekly numbers carry more noise, since a holiday or a storm can sink one week with no change in the underlying pace. Put alerts on the cumulative variance, which one bad week barely moves, and agree on the alert level before the year starts. AFP suggests a materiality threshold set as an amount, a percentage of budget, or both.

Which region owns the 144 jobs?

Break the cumulative variance into parts that add back to the total. AFP's advice is to find the root cause by dividing a variance into price, volume, mix, timing, or similar parts, and it warns that the net figure "can hide two large movements that need separate explanations." For an operations target, the first cut is region or team. Gravity's guide to tracing why a metric changed covers other cuts.

RegionGoal, weeks 1 to 26ActualVarianceVariance %Share of net varianceVariance, weeks 21 to 26
North598558-40-6.7%28%-16
Central897905+8+0.9%-6%+2
South897785-112-12.5%78%-6
Total2,3922,248-144-6.0%100%-20

South explains 112 of the 144 jobs. Against a Q2 goal of 42 a week, it completed 26 to 28 until the crews arrived in week 21, and it has averaged one job a week below goal since. Its weekly pace has recovered, and the 112 missing jobs are still missing.

North has the smaller gap and the more stubborn trend. It is 40 behind and still runs about 3 jobs a week short of its goal of 28, for 16 short over the last six weeks. If that pace holds through the second half, North adds roughly 70 more jobs to the gap. Central is 8 ahead, which offsets a small part of the shortfall.

The catch-up then needs an owner. If South recovers its own gap, it needs 44.8 jobs a week for the rest of the year against a plan average of 40.5, a 10.6% lift. North needs 28.5 a week against 27.0. Ask each regional manager whether that pace is staffed before it goes into the plan.

Writing the week 26 note

AFP's advice on commentary is to "explain what caused each material variance, how it occurred and what it means going forward." A weekly operations note turns that into three short parts: what happened, why, and what changes next week. Keep it under 150 words, open with the cumulative position, and name an owner for each change.

The note for week 26 could read:

Week 26: 108 jobs against a goal of 112 (-4). Year to date: 2,248 against 2,392, 144 behind (-6.0%).
South accounts for 112 of the 144. Its seasonal crews started in week 21, seven weeks after the plan assumed, and South ran about 15 jobs a week short until then. Since week 21 it has averaged one job a week below goal. North is 40 behind and still runs about 3 a week short.
To finish at 5,200, the team needs 113.5 jobs a week against a plan average of 108, or 134.6 a week in Q3. Next week, the North manager confirms whether the Q3 goal of 32 a week is staffed, and operations decides whether South's seasonal crews stay through Q4 to recover its gap.

Adjectives such as "strong" or "soft" tell the reader nothing until a number stands beside them.

Who runs the check on Monday morning?

A spreadsheet is the right place to start. Every formula is visible, and anyone on the team can open it and check a number. Its cost is the weekly routine: someone pulls the actuals, pastes them in, checks the totals, and writes the note.

Planning platforms suit teams where finance owns the plan. Workday Adaptive Planning, for example, documents variance reports that show the difference between versions such as actuals, budget, and forecast, and targets that already live in one belong there. A BI dashboard can show the same table every Monday, but someone still has to read it, judge whether the gap matters, and tell each manager. That last problem has its own article: Gravity's guide to automating weekly executive reports without another dashboard.

A team can also hand the Monday routine to Orion, the analytics platform from Gravity, after showing it how the check works. The targets can stay in the Google Sheet that holds the template, linked to the project with the Google Sheets integration. Rules a sheet cannot hold become Context pages that Orion consults on every run: what counts as a completed job, how reopened work is counted, and how large a gap must be before a regional manager gets a call.

Run the first few weeks side by side, with Orion's weekly comparison checked against the spreadsheet. When they agree, the analyst can ask for a Monday Workflow. Orion builds it and runs a test pass, and nothing is saved or scheduled until the team approves. Each Monday after that, the Workflow compares the week's actuals with the plan and highlights the regions behind the variance.

Inside the Workflow, a decision step checks each run against the team's alert rule, written as an ordinary sentence such as "alert only when cumulative actual is below 97% of cumulative goal," and passes the note to the regional managers only when the rule is met. Applied to the table above, that rule would first fire in week 15. Some causes never appear in the data, such as the week South's crews arrived, so Orion asks the team and proposes a Context page from the answer, which waits for the team's approval.

What a gap found at week 26 costs

The review needs the cumulative variance, the region behind most of it, and the required weekly rate set beside the plan's own average. With those on the table, it can settle who closes the gap and by when.

In the example, South's weekly pace is already back near goal. The open questions are whether its added crews stay long enough to recover 112 jobs, and whether North gets the staff to close a 3-a-week shortfall now. Found at week 26, the gap needs about 5% more pace over the rest of the year, against 20% if the team leaves it to the last eight weeks.